The design was elaborated in a Technical Detailed Design phase.
Phase of construction: put into operation in August 2015.
Time of Construction: 09.2014 - 08.2015
The design comprises rehabilitation of the municipal roads networks, consisting of 8 roads with overall length of 19 km. The design stipulates the following construction works: re-asphalting of the asphalt pavement; re-lagging of the road shoulders; demolition of the old elastic fence and construction of a new one; construction of roadside ditches and drainage facilities; stabilization of the roadside slopes; construction of a whole new road marking and vertical signaling;
As a result of the execution of this project, the 8 roads have been rehabilitated, their technical and operational specifications have been improved, and their time of operation prolonged.