  • Откриване на строителната площадка - 10.2014г.

 

The design was elaborated in a Technical Detailed Design phase.
Phase of construction: put into operation in August 2015.
Time of Construction: 09.2014 - 08.2015
The design comprises rehabilitation of the municipal roads networks, consisting of 8 roads with overall length of 19 km. The design stipulates the following construction works: re-asphalting of the asphalt pavement; re-lagging of the road shoulders; demolition of the old elastic fence and construction of a new one; construction of roadside ditches and drainage facilities; stabilization of the roadside slopes; construction of a whole new road marking and vertical signaling;
As a result of the execution of this project, the 8 roads have been rehabilitated, their technical and operational specifications have been improved, and their time of operation prolonged.

 

 

Urgent reconstruction works on the bridge at Belichka River, in Boben district of Herakovo village, Bozhurishte Municipality

This project of reconstruction of the bridge, will ensure the necessary structural reliability of the bridge and hassle-free passage of heavy vehicles and oversized agricultural machinery over it.


Phase of construction: put into operation in October 2015.
Time of Construction: 06.2015 - 10.2015
The design comprises rehabilitation of the municipal roads networks, consisting of 3 roads with overall length 13 km. The design stipulates the following construction works: re-asphalting of the asphalt pavement; re-lagging of the road shoulders; demolition of the old elastic fence and construction of a new one; construction of roadside ditches and drainage facilities; stabilization of the roadside slopes; construction of a new road marking and vertical signaling;
As a result of the execution of this project, the 3 roads have been rehabilitated, their technical and operational specifications have been improved, and their time of operation prolonged.


Phase of construction: commissioned and put into operation on 09.10.2015.
Time of construction: 06.2015 - 10.2015.
The design was elaborated in two phases. Detailed Technical Design (2012); and Detailed Work Design (2013), after the approval of the Detailed Technical Design.
The design comprises: modernization of the sport ground; construction of a running track; construction of a basketball playground; construction of a track for long jump; rehabilitation of the volleyball playground; rehabilitation of the benches at the stadium, the commenters’ post, the administrative building, the warehouse for sports equipment and materials and the restrooms for visitors;
New volleyball sport hall has been designed. The hall is equipped with HVAC system, lighting and visitors’ benches.
New open-work fence surrounding the whole complex has been designed. Parade main entrance for the complex has been designed also.